I-64 RIVERFRONT EXPRESSWAY 
Kentucky Department of Transportation: June – July 2007.
All of Gohmann Asphalt and Construction’s
divisions took part in this project.
This was a $53,000,000 project for the complete reconstruction
of I-64 from I65 to the Sherman Minton Bride, approximately 9
miles. The construction on this project was required to be
completed during three weekend closures and one thirty day
closure. Gohmann completed this project ahead of schedule
earning the maximum bonus of $2,000,000.
During the first three weekend closures the majority of the
western two miles of the project was required to be completed.
This work included the removal of the existing pavement, 
removal and replacement of the subgrade then reconstruction
of the highway with Hotmix Asphalt Pavement.
During the thirty day road closure, this project required the removal
and replacement of all bridge joints, all bridge decks were milled,
patched and all barrier wall was either replaced or patched and
sealcoated. Also all bridge decks were overlaid with a Rosphalt, a
waterproof asphalt membrane and all concrete driving lanes
were removed and replaced with Hotmix Asphalt Pavement.
This project was successfully completed ahead of schedule.